Initial Diagnosis.
Budget for the planned work normally needs to be
determined as accurately as possible prior to work
commencing. The vessel should be slipped and test
peels done in several places. A professional surveyor
with sound knowledge of osmosis problems and repair
should be contracted to report. The boat owner will
then have a realistic view as to the degree of osmosis
repair required. |
Peeling the hull
using a Gelplane.
This hand-held tool will cut to 1.25mm deep by 75mm
wide and is a fast, efficient means of removing
affected gel-coat, chopped strand or woven roving. The
photos below show the hull of a 90' power boat
undergoing the process. Total peeled area for the
vessel amounted to 7,500 square feet and this phase of
the work was completed in 5 weeks.
Photos show peeling in progress, a blister void at
3rd peel, 4 layers removed and a section for repair.
|
Drying and post-cure.
The object is to get the moisture content of the hull
down to an acceptable level for relaminating.
Post-cure is also desirable to dry/remove any uncured
resin and osmotic fluids. The HotVac system which uses
a combination of heat and vacuum is an efficient
method of drying and post-cure. All internal moisture
must be removed from the hull as soon as the vessel is
slipped. Floors are lifted and air-flow through the
interior is maximized by opening hatches, use of fans
etc.The HotVac system is fast but a stabilisation
period is recommended whereby the hull is allowed to
air dry inside and out for up to a month. Sometimes,
when moisture has penetrated stringers and other
foam-filled structural areas, penetrating infra-red
heat will be required.
These photos show moisture from internal stringers
and the HotVac system in operation.
|
Preparing the work area.
Working on a covered slipway presents problems such as
lack of height and space, difficulty moving equipment
etc. To improve workspace the whole area under
the vessel must be floored with plywood sheets. A
preparation [wetting-out etc] room is made under the
stern of the boat.
Sand-blasting.
In order to remove all dried, potentially
reactive material from the original lay-up the hull is
sand-blasted with garnet grit. This process also gives
an ideal 'keying' surface for any epoxy to be applied.
|
Water-blasting.
The hull is high pressure washed several times after
sand-blasting to remove any acidic material. Ph level
is tested and water washing continues until Ph is the
same as the water being used for washing. The hull is
then left to dry for 24-48 hours.
|
Tenting for
environment control.
If local temperature and humidity are not within the
accepted limits for epoxy application the hull must be
tented so dehumidifiers and air conditioning may be
used for environment control. A tent is initially
built for sand-blasting to control emissions. To help
control temperature and humidity a 2nd tent is built
inside the 1st to provide double insulation. Humidity
readings outside in HK at this time range from 84% to
100%, temperature is normally around 32C. Ideal
working conditions for applying epoxy and laminate are
humidity below 70% and temperature 23-25C. With
current outside conditions a partitioned room 30' x
25' needs four 20,000 Btu air conditioners and two
dehumidifiers to maintain ideal working environment.
|